Contract Supervision – DCA Consulting Engineers

 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2022-23 R150m Special Maintenance on National Route R63 Section 12 from N10 (Km 0.0) to Bedford (Km 20.7) Recycling of the existing pavement surface and base layers combined with bitumen and cement to produce 155 mm BSM2 base layer, cape seal surfacing, construction of RC box culverts and drainage. GladAfrica
Chief Resident Engineer 2018-20 R394m Lesotho Highlands Development Project, Phase II – Advance Infrastructure Contract CRE for construction of advance infrastructure comprising roads, water, sewer reticulation, temporary and permanent water and sewer works, bulk excavations and terracing at Polihali Dam site and infrastructure upgrading at Katse Dam site. Mott MacDonald Africa
Resident Engineer 2016-18 R396m Safety Improvements on R23 Section 2 from Km 0-Km 4 and 6 new bridges Standerton – Balfour E R for contract to construct approach roadworks at bridges and demolition of existing bridges and rebuilding 6 new bridges along R23 SMEC

 

Bridal Veil Road Overpass Bridge
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Engineer’s Representative 2014/2016 Completed R71,5m Bridal Veil Road Overpass Bridge over N1 20 leading into the Mall of Africa E R for contract during the construction of the Bridal Veil Road Overpass Bridge, carrying four 3.5 m traffic lanes, a 2 m pedestrian walkway and a 2 m cycle track over the N1. The bridge consists of five precast M-beam and slab configuration. The bridge piers comprised multiple columns with transom beams founded on spread footings and the abutments consist of perched structures founded on augured piles with mechanically stabilized earth embankments constructed after piling. AECOM

Richmond Pipeline
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Engineer’s Representative 2013/2015
Current
R205m Richmond Pipeline, Reservoir
& Pump Station
E R for 3 contracts during the construction of a 32 km welded steel 450 / 600 dia pipeline, 5 MI concrete reservoir, pump station, supply and installation of pumps, pipework and motor control centres. RHDHV

Ohlanga Sewage Transfer Scheme – Umhlanga Rocks
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2010-2012 R145m Ohlanga Sewage Transfer Scheme – Umhlanga Rocks R E during the construction of a new 12 Ml/day pump station, supply and installation of pumps, pipework and motor control centres, 1,1km * 560mm dia HDPE rising main and 6,2km gravity outfall sewer and 1,33km 1350mm dia elevated concrete pipe on P/T concrete beam bridges. Aurecon

King Shaka International Airport – La Mercy Durban
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Chief Engineer’s Site Representative Civil 2007-2010 R1,6b King Shaka International Airport La Mercy Durban Site Supervision of Aprons and associated taxiways, public open parking facilities, underground services at the terminal precinct , external airside/landside road and general civil co-ordination during the complete project construction period. PDNA

Remote Parking Facility ACSA – Durban

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Design Engineer 2007 R16m Remote Parking Facility  ACSA at Old Durban International Airport Design of remote parking facility infrastructure to supply additional capacity to existing facilities. ARCUS GIBB

Multi-storey Car Park ACSA – Durban

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2006/7 R94m Multi Storey Car Park for ACSA at Old Durban International Airport R E during construction phase of two floor R/C parking garage comprising grout auguered piles, post tensioned slabs and structural steel barrel vault roof structure. Project stopped midway due to construction of new KSIA airport. ARCUS GIBB

Multi-storey Car Park ACSA – Durban

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Design Engineer 2006 R8m Multi Storey Car Park for ACSA at Old Durban International Airport Design of civil works infrastructure consisting of stormwater drainage, sewer, water reticulation and traffic drop off facilities. ARCUS GIBB

Montebello Hospital

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Design Engineer 2005 R2,5m Montebello Hospital Design of civil and structural additions. ARCUS GIBB

Groutville Low Cost Housing Development

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Design Engineer 2004 R10m Groutville Low Cost Housing Development Preparation of preliminary infrastructure designs, cost estimates and Bulk Services Reports for Driefontein, Etsheni, Njekane and Mnyundwini in KwaDukuza. ARCUS GIBB

Reunion Eco Centre – Isipingo

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Design Engineer & Contract Supervision 2004 R5,5m Reunion Eco Centre and Boardwalk Preparation of structural design drawings for Eco Centre building and polywood boardwalk through mangrove swamps. ARCUS GIBB

SATI Container Depot – Southgate

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2003 R16,7m SATI Container Depot Southgate 40 000 m2 container storage depot, comprising layerworks, precast block paving, rail siding and infrastructure. ARCUS GIBB

Westville Sewer Reticulation

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2002 R5m Westville Sewer Reticulation  Installation of sewer reticulation in existing erven in Westville comprising 17 100 m of 160 upvc sewer pipes and 660 precast concrete manholes in Phase 4, Stages 1 and 2. SOOKAN & Associates

NR2 La Lucia Interchange – Umhlanga Rocks
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2002 R6m NR2 La Lucia Interchange Upgrading Part time supervision to completion of the rehabilitation of existing carriageways under extremely heavy traffic conditions, mill/replace, and final premix overlay comprising 21 000 m2 on MR 94 and ramps, measurement of quantities on completed road and bridge works and final acceptance inspection. BCP Engineers

The Moreland Millenium Bridge – Umhlanga Rocks
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2002 R8m The Moreland Millennium Bridge Two span closed cell box structure, curved soffit, skew, on l/grade, founded on precast piles, elliptical central pier, conventional counterfort abutments, structural steel arches mounted on steel fins carrying lighting components. BCP Engineers

Widening of Old Bush Bridge – Umhlanga Rocks
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2001 R1.5 Widening of Old Bush Bridge Two span closed cell box structure, closed abutments, central pier, prestressed road / road widening bridge founded on Berea Red sands. BCP Engineers

Widening of Seaview Bridge on Umhlanga Rocks Drive
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2000 R4m Widening of Seaview Bridge on Umhlanga Rocks Drive Widening of Seaview Bridge on Umhlanga Rocks Drive : Two span closed cell box structure, counterfort abutments, central pier prestressed road / road widening bridge founded on Berea Red sands. BCP Engineers

Widening of Umhlanga Rocks Drive
 

FUNCTION YEAR VALUE PROJECT DESCRIPTION CONSULTANT
Resident Engineer 2000 R2m Widening of Umhlanga Rocks Drive Rehabilitation of existing carriageways, construction of new three lane carriageways, all associated bulk earthworks and layerworks comprising 20 000 m2 premix overlays under extremely heavy traffic conditions between Hickory Drive and Armstrong Avenue. BCP Engineers